Fuel leak will delay first launch of NASA’s Artemis lunar rocket by weeks


Content of the article

CAPE CANAVERAL — For the second time in a week, NASA aborted a launch attempt for its giant next-generation rocket on Saturday, citing a stubborn fuel leak that the space agency says could delay its first moon mission to Mars Artemis program of at least several weeks.

Preflight operations were canceled for the day approximately three hours before the targeted 2:17 p.m. EDT (6:17 GMT) liftoff time for the 32-stage Space Launch System (SLS) rocket and its Orion capsule from Cape Canaveral , in Florida.

Advertisement 2

Content of the article

Content of the article

The uncrewed test flight, aimed at launching the capsule to the moon and back, was to mark the maiden voyage of the SLS and Orion half a century after Apollo’s last lunar mission, precursor to the Artemis program.

The countdown was canceled after Kennedy Space Center technicians made three unsuccessful attempts to repair a “large” leak of supercooled liquid hydrogen propellant being pumped into the rocket’s core stage fuel tanks, a report said. agency officials said.

Monday’s first launch attempt was also foiled by technical issues, including another leaky fuel line, a faulty temperature sensor and cracks found in the foam insulation.

Mission leaders made a second launch attempt on Saturday once previous issues were resolved to their satisfaction. And NASA had reserved another backup launch time, Monday or Tuesday, in case a third test was needed.

Advertisement 3

Content of the article

But after a review of data from the latest difficulties, NASA concluded that the new hydrogen leak was too tricky and was taking too long to complete troubleshooting and repair the launch pad before the current allotted launch period expired. at the mission on Tuesday.

The delay means the first opportunity to try again would present itself during the next launch window, which runs from September 19 to 30, or during a later October window, said NASA associate administrator Jim Free, to journalists during a late afternoon briefing.

He said the postponement would also involve bringing the spacecraft back to its assembly building, in line with Cape Canaveral ‘scope’ rules limiting how long a rocket can remain at its launch tower before undergoing another round. internal security checks.

Advertisement 4

Content of the article

Mike Sarafin, NASA’s Artemis mission manager, said efforts to resolve the latest technical issue would take “several weeks of work”.

NASA chief Bill Nelson said earlier today that a rollback would postpone the next launch attempt until at least mid-October, in part to avoid a scheduling conflict with the next crew of the International Space Station which was to be launched earlier this month.

Launch-day delays and malfunctions are not uncommon in the space sector, especially for new rockets such as NASA’s Space Launch System, a complex vehicle with a set of pre-launch procedures that does not have not yet been fully tested and rehearsed by engineers without a hitch. .

On average, the odds of rubbing a launch on any given day for any reason, including bad weather, are about one in three.

Advertisement 5

Content of the article

“We’re not going to launch until it’s correct, and that’s standard operating procedure, and will continue to be that,” Nelson said during the briefing.

The last-minute setbacks on the launch pad came at the end of a decade-plus development program, with years of delays and billions of dollars in cost overruns on SLS and Orion contracts. respectively of NASA with Boeing Co and Lockheed Martin Corp. .

MOON TO MARS

In addition to its technical challenges, Artemis I marks a major turning point for NASA’s post-Apollo human spaceflight program, after decades focused on low Earth orbit with space shuttles and the International Space Station.

Named after the goddess who was Apollo’s twin sister in ancient Greek mythology, Artemis aims to get astronauts back to the moon’s surface as soon as 2025, although many experts believe that deadline is likely to slip.

Advertising 6

Content of the article

Twelve astronauts walked on the moon during six Apollo missions from 1969 to 1972, the only spaceflights to still place humans on the lunar surface. But Apollo, born out of the US-Soviet space race during the Cold War, was less science-driven than Artemis.

The new moon program has enlisted commercial partners such as SpaceX and space agencies from Europe, Canada and Japan to eventually establish a long-term lunar operating base as a springboard to even more ambitious human journeys to Mars. .

The launch of the SLS-Orion spacecraft is a key first step. Its maiden voyage is meant to put the 5.75 million pound vehicle through its paces in a rigorous test flight pushing its design limits and aiming to prove the spacecraft is fit to fly astronauts.

Advertising 7

Content of the article

If the mission is successful, a crewed flight of Artemis II around the moon could take place as soon as 2024, followed in a few years by the first lunar landing of the program of astronauts, including a woman, with Artemis III.

Considered the most powerful and complex rocket in the world, the SLS represents the largest new vertical launch system NASA has built since the Apollo-era Saturn V.

Although no humans are on board, Orion will carry a simulated crew of three – one male and two female mannequins – equipped with sensors to measure radiation levels and other stresses that real astronauts would experience.

(Reporting by Joey Roulette in Cape Canaveral, Florida, and Steve Gorman in Los Angeles; Editing by Lisa Shumaker, Frances Kerry, Chizu Nomiyama and Jonathan Oatis)

Advertising

comments

Postmedia is committed to maintaining a lively yet civil discussion forum and encourages all readers to share their views on our articles. Comments can take up to an hour to be moderated before appearing on the site. We ask that you keep your comments relevant and respectful. We have enabled email notifications. You will now receive an email if you receive a reply to your comment, if there is an update to a comment thread you follow, or if a user follows you comments. See our Community Guidelines for more information and details on how to adjust your email settings.